|
ANNOTATED
OUTLINE
OF TERMS |
|
|
FIRST
PHASE
|
|
1.
The Airport Authority may construct a 14-gate,
approximately 250,000-square foot replacement terminal, including
baggage and concessions.
·
The Framework
provided for a 14-gate terminal of 330,000 square feet, not
including up to 35,000 square feet for Airport Authority offices. The size of the proposed terminal in the Framework was
negotiated based on very rough estimates of required space, not
connected to a precise analysis of the terminal needs . In fact,
the proposed terminal size envisioned in the original Framework is
larger than necessary to serve the number of passengers that are
expected to use a 14-gate terminal.
·
The Authority
and the City have agreed that it is reasonable to plan the
terminal to accommodate 6.7 million passengers annually by the
year 2015. As
explained below, it is highly probable that the 6.7 million
passenger level will not be reached until many years after 2015.
For planning purposes, however, it makes sense to provide
for a worst-case scenario. This
planning horizon and approach is consistent with industry
practice.
·
The 14-gate
terminal will come close to serving the full projected demand with
adequate levels of service consistent with industry standards. Additional gates (as provided in phase II) would ensure
appropriate service quality as the traffic levels approach the
design objective of 6.7 million annual passengers.
·
In negotiating
the Framework, it would have been better if both sides had
analyzed in detail the exact design specifications of the proposed
terminal, but everyone was under considerable time constraints at
that time and there were many other terms that were much more
important for both parties. The
new figures are the result of greater thought and analysis and
will be able to meet the Airport’s actual needs in terms of fire
and building codes, ADA and industry standards for levels of
service in terminal facilities.
|
|
2.
The Authority may use a total of 5,000 parking spaces west
of Hollywood Way for public parking.
·
The Framework
provided that the Airport Authority could build 5,000 parking
spaces west of Hollywood Way, but did not clarify whether this
limitation applied to all parking spaces or just public parking
spaces. The proposed Outline clarifies that the limit applies only
to public parking spaces, not to spaces for employees or rental
cars. In addition,
this proposal uses the term “use” since it was unclear what
the parties meant in the Framework by “construct.”
|
|
3.
The Authority will secure federal authorization for and
will implement and permanently enforce a mandatory 10 p.m. to 7
a.m. curfew on all flights (with exceptions for medical, weather,
and mechanical emergencies).
·
One of the
core understandings of the Framework was that a terminal would be
built only once there was meaningful nighttime noise relief.
The Framework would have allowed the Authority to build a
14-gate terminal in the first phase if it implemented a nighttime
closure of the terminal that would have had the practical effect
of halting all nighttime commercial operations.
All the parties at the time believed that that approach
would have to provided interim noise relief without going through
extensive federal approval process.
Unfortunately, the FAA indicated that it considered the
terminal closure to constitute a curfew that legally could not be
implemented without following the elaborate federal approval
processes. Thus, the
basis for this pillar of the Framework deal was removed.
·
FAA
Administrator Garvey acknowledged last month that meaningful
nighttime relief is a core element of any terminal replacement
agreement and that a curfew showed real promise for being
approvable under federal law and for providing the necessary noise
relief. She promised
to expedite the Part 161 Study.
We expect that Garvey’s commitment will mean that the
curfew can be studied and implemented within about 18 months –
considerably less than the 4 years for the more extensive study
originally proposed.
·
Based upon
advice from the FAA, we believe that a curfew can be obtained in
18 months or less – if the Authority limits its Part 161 Study
to a curfew at this time and does not include other possible noise
relief measures in the study.
|
|
4.
The Authority will implement a funding mechanism to finance
insulation of at least 50% of all homes within the 65 dB CNEL, as
depicted on the 1998 FAA-approved noise exposure map, and will
complete insulation on 30% of homes prior to occupancy of the new
terminal and agree upon a timetable for completion of all sound
insulation.
·
These noise insulation terms incorporate the
provisions of Phases I and II of the Framework.
·
As of 1998, there were approximately 2200 homes
within the 65 dB CNEL contour in Los Angeles and Burbank.
The Airport Authority has committed in a proposed agreement
with the City of Los Angeles to treat homeowners in Burbank and
Los Angeles equally, meaning that a total of approximately 733
homes in both cities would have to have been insulated by the time
the new terminal is occupied.
|
SECOND PHASE
|
|
5.
The Airport Authority may expand the terminal up to a total
of 16-gates, and approximately 280,000 square feet including
baggage and concessions.
·
The Framework’s Phase II also would have
allowed a 16-gate terminal. However,
a 370,000-square-foot terminal (as contemplated by in the
Framework) is larger than needed to accommodate the 6.7 million
passengers for which the City and the Authority have concurred
should be the design capacity for the 16-gate terminal.
·
Like the Framework, this Outline is silent on the
timing for when the Authority
builds the additional gates – but other provisions of the
Outline encourage the Authority to begin the process for
additional gates once growth in passenger traffic makes the
additional gates advisable.
·
The proposed design capacity of the terminal will
accommodate reasonable growth at the Airport at least until 2015
– and probably much longer given past growth patterns at the
Airport. While it is
always difficult to predict future growth, historical data shows
that a capacity of 6.7 million annual passengers provides ample
growth potential. From
1995 through 1999, the number of passengers using the Burbank
Airport actually declined by almost 5 percent as shown in the
table below. That
decline occurred when the national, state and regional economies
were booming. The
Joint City/Airport Traffic Study assumes the new terminal will
open in 2003 with 5 million annual passengers and then grow at 2.5
percent per year until 2015 when it reaches 6.7 million
passengers. Based on the actual decline during the last 5 years, a 2.5
percent growth rate is extremely optimistic.
If the growth rate were 1.5 percent per year, it would take
until 2023 to reach 6.7 million passengers.
At 1 percent per year – still much faster than the
current trends would justify -- it would be 2033 before 6.7
million annual passengers were reached.
Airport Passenger Traffic
1995 -
4,972,575
1996 -
4,838,483
1997 -
4,717,688
1998 -
4,731,656
1999 -
4,736,293
|
|
6.
The Authority may use an additional 1,000 parking spaces,
up to a total of 6,000 parking spaces west of Hollywood Way.
·
This measure
is the same as in Phase II of the Framework with the clarification
mentioned above with respect to excluding employee and rental car
parking and substitution of the term “use” instead of the word
“construct” in the Framework.
|
|
7.
The Authority will
secure federal authorization and will permanently enforce a noise
budget. The required
study and application for federal approval must be initiated once
passenger traffic at the Airport has grown by 10 percent above
today’s levels. The
budget will impose a limit on the community noise burden
(expressed as the average Leq noise level at the 18
permanent noise monitoring stations) at current levels.
The intent is that (a) community noise burden would never
be greater than it is today, (b) the Airport would be able to
accommodate reasonable commercial growth (up to 6.7 million annual
passengers) without significant commercial aircraft substitutions,
and (c) additional growth in passengers beyond that level could be
achieved within the limit set by the budget only if quieter
aircraft are substituted for noisier aircraft.
·
The Framework required the imposition of
restrictions on noisy Stage II and hushkitted jets that create a
disproportionate amount of the noise at the Airport.
However, FAA expressed great concerns about these
provisions, citing two issues: national and international disputes
relating to restrictions on these jets and the rigidity of an
outright ban. Because
FAA would have to approve the restrictions on hushkitted jets,
FAA’s concern suggested that Phase II of the Framework would be
very difficult to attain.
·
We have come to learn from hours and hours of
discussions with the FAA and the Authority that Burbank can
achieve its noise relief objectives without the rigid provisions
of the Framework.
·
Accordingly, Burbank proposes to replace the
inflexible restrictions on Stage II and hushkit planes with a
noise budget. A noise
budget provides a flexible tool to limit noise in the most
efficient way possible while allowing aircraft operators and the
Authority the flexibility of deciding how best to allocate the
permissible limit on noise among the diverse pool of airport
users.
·
The budget has been carefully designed to achieve
the objective of not increasing the noise levels around the
airport. At the same
time, we wanted to ensure that the Airport had flexibility to
provide a reasonable level of growth.
Since the City and the Authority concur that the design
capacity of the terminal should be to serve 6.7 million passengers
annually, we asked our technical consultant to design a noise
budget that achieved the objective of preventing a degradation in
the noise environment while meeting the growth projections. The proposal satisfies these criteria.
·
Like the Framework approach with the bans on
stage II and hushkitted aircraft, this Outline contemplates that
the Authority will not immediately apply for authorization to
impose the budget. Instead,
the City proposes that the Authority not be required to seek the
budget until there has been substantial passenger growth (which
would necessarily be accompanied by growth in the number of
flights at the Airport).
·
If airlines or jet owners want to conduct more
flights beyond the design capacity of the terminal, they can do so
but only if they use quieter planes – because the noise levels
are subject to a limit based upon today’s noise levels.
·
This approach affords aircraft operators much
more flexibility than the simple ban on stage II and hushkitted
aircraft. Because a
flexible noise budget is much more likely to be approved by FAA ,
it makes it much more likely that a Phase II terminal could be
built
·
The noise budget is designed so that it is
practical for airlines to continue to operate their aircraft
without the need to make substitutions in types of aircraft (e.g.,
there is no need to substitute 757s for 737s) until the terminal
reaches its design capacity.
|
|
GENERAL
CONDITIONS
|
|
8.
Until such time as
the noise budget is implemented, the following supermajority
provisions shall apply. (a)
A supermajority Commission vote will be required to change the use
of, or reconfiguration of, any interior space in the terminal
building (based upon a space use plan incorporated in the
agreement). (b) Once passenger traffic has increased 10 percent above
today’s levels, a supermajority vote will be required to
authorize any capital project costing over $100,000 or to approve
or modify any use or lease agreement with any Airport tenant.
·
Growth will occur without affirmative action by
the Commission. The
supermajority voting requirement (approval by a majority of each
city’s delegation) is deemed necessary to prompt careful
deliberation by the Commission before it takes action that could
bypass the intent of the agreement between the parties.
Burbank needs the assurance that the design will not be
significantly reconfigured to expand its capacity beyond the
agreed-upon level.
·
While there are many Commission actions that have
the potential to result in growth, Burbank respects the need for
bright lines. Therefore,
we propose that supermajority voting will be required to approve
any change in the use of space in the terminal.
Burbank does not anticipate that this will result in
significant burdens on the Authority or Commission, or preclude it
from meeting reasonable passenger forecasts but is intended to
ensure that the intent of the agreement is preserved over time.
·
We believe that there should be positive
incentives for the Authority to seek a noise budget since that is
the provision of this agreement that replaces the stage II and
hushkit ban in the original Framework.
We have been told by the FAA that a noise budget is more
likely to be approved if it is not sought until several years
after the curfew has been implemented.
For this reason, Burbank proposes that the incentives for
applying for the budget not become effective until traffic has
increased substantially – 10 percent above today’s levels.
At that time, we believe that the agreement should include
incentives for success in seeking a budget.
·
The supermajority provisions are designed both to
provide an incentive for success of the budget application and to
provide meaningful protections against Authority-assisted growth
in the event that the noise budget is not approved.
·
If the Authority is successful in seeking a noise
budget, the supermajority provisions will not have any practical
effect.
|
|
9.
Final agreement will be conditioned upon issuance by the
City of all development approvals including those under PUC §
21661.6, general plan amendments and zoning and land use
entitlements no later than the effective date the final agreement.
·
City approvals were part of the original
Framework.
|
|
10.
The City’s execution of a final agreement will be
contingent upon preparation of whatever documentation is required
by law pursuant to CEQA.
·
This provision
was added to clarify that Burbank’s approval would be subject to
applicable CEQA requirements.
Because the City would have been subject to these
requirements regardless, this provision does not change the
substance of the original Framework.
·
The City is
unable to be more specific at this time about the particular scope
of analysis, if any, that will be required to satisfy CEQA.
The City has retained a consulting firm to review the
relevant technical considerations and provide a recommendation on
this issue. The City
hopes to be able to clarify its legal obligations within the next
few weeks.
·
Burbank is not
proposing to require anything more than the law requires.
We are not proposing a new federal EIS because that is not
required by law. We
doubt that CEQA will require us to prepare a new EIR.
Because the existing EIR is based upon data that is more
than 10 years old, we have a legal obligation to determine what
(if any) additional analysis is needed.
(The City has never issued any approvals for the terminal
project and, though the Authority has certified the existing EIR,
the City’s approvals constitute a new action under CEQA and
there is a considerable question as to whether the City legally
can rely upon the Authority’s EIR.)
|
|
11.
The City will buy key properties in the Runway 8 safety
area and sell an avigation easement and restrictive covenant to
the Authority for any such properties.
·
Burbank has
included this offer to address safety concerns at the Airport that
have been made clear by the recent runway overrun by the Southwest
Airlines 737. The
City has no obligation to purchase the runway safety area but
believes that this good faith offer should help improve safety at
the Airport.
·
The City and
the Authority would negotiate over which properties to purchase.
The City would purchase the properties and then sell to the
Authority such interests in the property as are necessary to
protect the safety of the areas.
|
|
12.
Should the
Authority initiate a Part 150 study of runway use patterns, it
will use safety as the overriding criterion for evaluating any
changes in use of Runway 8.
- The provision of the Framework that would have
barred eastern takeoffs caused concerns both for FAA and
neighboring communities.
FAA recently proposed addressing this issue in a
future, detailed study – the so-called Part 150 Study.
Burbank agrees that this proposed approach (that was
endorsed in a letter from the FAA to Congressman Rogan) would
allow all interests to be considered and addressed in a
comprehensive fashion. However,
it is critical for Burbank and the Authority to clarify that
safety must be the most important factor driving this
analysis.
|
|
13.
The Authority will strictly enforce all existing airport
noise rules.
·
This provision
was part of the original Framework.
|
|
14.
The Authority will
comply with the California Government Code Section 6546.1 ceiling
on the size of the Airport’s noise impact area as interpreted by
the California Court of Appeal.
·
This provision
was part of the original Framework, but the Outline clarifies that
the “noise impact area” is defined pursuant to its proper
meaning under state law as decided by the California Court of
Appeal.
|
|
15.
The Authority will implement a policy of rotating the
Commission Presidency among the 3 cities to ensure that at least
one Commissioner appointed by each city shall serve as Commission
President for at least three out of each ten (10) year period.
·
The provision
was part of the original Framework.
|
|
16.
The Authority will waive all legal claims.
·
This provision
was part of the original Framework.
|
|
17.
The Authority commits maximum legally permissible
mitigation funding for:
(a) Transportation infrastructure mitigation as recommended
in the joint traffic study
(b) Mass transit design and
dedication of right-of-way
(c) Participation in a
transportation management organization (TMO)
(d) Impact fee for police and fire
($.12 per new square foot) and not for library and parks ($.38 per
new square foot).
(e) Sewer facility charges
(f) New water and electric distribution facilities
·
The City has
had several discussions with the FAA regarding the Authority’s
responsibility to comply with federal requirements on the use of
airport revenue. Minor
modifications have been made to the certain provisions of the
Framework dealing with payments to the City to ensure compliance
with the FAA’s views on these federal standards.
·
The Authority
and the City have jointly commissioned a traffic study to assess
traffic impacts from the new terminal.
Nevertheless, the FAA has told us that that agency would
strenuously object to certain expenditures by the Authority for
traffic mitigation and mitigation of other Airport impacts that
occur off Airport property. We
believe that the FAA is wrong in their interpretation of federal
legal requirements but we have proposed not to challenge the
FAA’s view.
|
|
18.
The Authority will make an annual payment in lieu of taxes
(PILOT) in the amount of property tax otherwise payable to the
City or the Burbank Redevelopment Agency on Airport property were
such property taxable. The
PILOT will be offset by payments made in the previous item if
required under federal law.
·
The City has worked with the FAA to ensure that
this requirement complied with federal limitations on the use of
airport revenue. The
FAA has agreed that the PILOT may be allowable but has demanded
that the parameters of this payment be better defined and that
steps are taken to ensure that the Authority was not paying twice
(once under the PILOT and once under the mitigation payments) for
the same expense. The
minor changes reflected in the Outline respond to these concerns.
·
Since we do not know the amounts of mitigation
costs (which would have been the responsibility of the Authority
under the Framework or under applicable state law), the PILOT has
been modified from the Framework to remove the ceiling on the
annual payment.
·
The intent is unchanged from the original
Framework: the Authority will make payments to compensate the City
for lost property tax revenue and for mitigation costs associated
with growth in the Airport and Airport traffic.
|
|
19.
The City shall not increase the tax rate applicable to
transient parking at the Airport during the time that bonds issued
to finance development of the new terminal remain outstanding.
·
This provision
was part of the original Framework.
|
|
20.
The Authority and the City will agree on revisions to
language in the residential avigation easements, which shall
ensure that the Authority will be responsible for providing
additional noise attenuation or other remedial work on a
previously noise insulated home if the interior noise level of a
home exceed pre-established limits
·
This provision
was part of the original Framework.
|
|
21.
The Authority will design all construction on the B-6
Property in an appropriate manner that recognizes aviation history
and complies with the City’s Art in Public Places requirements.
·
This provision
was part of the original Framework.
|
|
22.
The City and the Authority will dismiss all pending
litigation with a stipulated order that incorporates the terms of
the final agreement.
·
This provision
was part of the original Framework.
|
|
23.
The use of and construction on the B-6 property will be
formally limited to the footprint of a 16-gate terminal (and
related facilities) as set forth in an Airport Layout Plan that
will be attached to the final agreement.
·
This provision is intended to clarify that the
City approvals that would accompany a final agreement are intended
to provide approvals only for the terminal and related facilities
set forth in the agreement and that modifications to the project
would require future City approvals.
(See discussion above on supermajority voting to change the
internal space usage in the terminal.)
·
This provision is analogous to the restrictions
that appear in similar City land use approvals for large,
integrated projects.
|
|
24.
The City will release the Authority from covenants and deed
conditions contained in Property Transfer Agreements except as
provided in the final agreement.
·
This provision was not part of the original
Framework but appears in the Title Transfer Agreements.
The City believes that the parties always intended for the
City to give such a release upon a final agreement.
This is intended to clarify the original intent.
|
|
25.
The Authority will demolish the existing terminal and
impose use restrictions on future use of site.
·
This provision
was part of the original Framework.
|
|
26.
The substantive terms will be memorialized in the
appropriate legal vehicle(s) -- an amendment to the Joint Powers
Agreement, a development agreement, deed restrictions or court
orders -- depending upon
advice from the FAA.
·
In the
Framework, all of the substantive provisions would have been
contained in a Development Agreement (as well as other specialized
agreements for particular purposes).
However, FAA has indicated that it would vehemently oppose
such an approach that would tie the final agreement to the
City’s exercise of its zoning and land use approval powers.
·
The FAA has
recommended, as an alternative, that some of the terms of the
final agreement be prepared as amendments to the JPA
Thus, Burbank proposes changes in the means of
memorializing the deal to address FAA’s concerns.
Burbank would work with the Authority and FAA on the
precise mechanisms that satisfy the FAA’s views on the
appropriate legal vehicles for achieving our mutual objectives.
|